Episode Overview
Most major projects manage risk in Excel, when they manage it at all. Matt Mitchell got there the other way around: from IT and software development, through Enron’s formal risk training and a global risk platform he rolled out to customers, to the customer itself, Noble Energy, where he became risk lead on some of its very largest projects, including Leviathan, the offshore gas platform in the Mediterranean sanctioned at roughly $3.9 billion. In 56 published minutes with Orion Matthews he delivers the most practical risk 101 the show has run: what risk actually is (a deviation from your objectives, in either direction), how to split a register so the project team can breathe, how to run a workshop that never starts from a blank screen, and why, in risk culture, one is greater than zero.
One is greater than zero
“It’s just about getting in there and doing it. Get in and start a risk register and begin working through what that whole process looks like.” ~20:50
The software-to-risk path
Enron risk training, then a risk-software platform he rolled out to customers, then a decade owner-side at Noble Energy: the rare risk lead who has built the tool, sold the tool, and lived without it.
Two registers, one project
On Leviathan the commercial risks (selling gas to Egypt, the geopolitics) got their own register, so the execution register could stay focused on what the project team could actually control.
“My favorite icebreaker is, you show up for a first meeting and say, ‘I’m from corporate. I’m here to help.’ And you always get a bunch of laughter.” ~41:10
A written companion to the released episode, built from the full transcript. Quotes are verbatim, lightly condensed for readability: false starts and fillers removed, meaning untouched. Timestamps are approximate: they follow the transcript’s minute markers, which run about 14 minutes long of the 56-minute published cut, so read them as positions in the conversation rather than the published audio. Biographical facts come from Matt’s public LinkedIn profile and what he says on the show; the talk-time and word-count tiles are computed from the transcript. Banner photos of the Leviathan platform are license-verified (CC BY-SA 4.0; credits below).
Episode Timeline
The conversation as it actually unfolded: twelve chapters, following the show’s four-act arc. The strip below maps each chapter’s share of the recorded conversation; timestamps are approximate. Click any block to jump to its chapter.
Act II is the engine room: three quarters of the conversation lives in the mechanics, the workshop psychology and the P-numbers. Timestamps follow the transcript’s markers, which run about 14 minutes long of the 56-minute published cut.
From Software to Risk Lead
The welcome, the résumé in one breath, and the unusual on-ramp: Enron risk training, a risk platform, and the customer who needed someone to run it.
Leviathan & the Two Registers
An FPSO becomes a massive platform, FID at roughly $3.9B, and the decision to split commercial risk from execution risk.
Risk 101: Deviation from Expected
The ISO definition, the COSO case for treating overshoot as risk, the valve test, and where the black swans live.
Making Risk Economical
The project-specific risk matrix as the exchange rate, and the risk champions program that scaled one risk manager across a portfolio.
Inside the Risk Workshop
The first Leviathan workshop, personality management, eliciting from the quiet experts, and never starting from a blank screen.
The Flywheel & the Politics of Risk
Piggybacking the monthly reviews, the witch-hunt problem, no-blame lessons learned, and the ancient jugs on the sea floor.
Monte Carlo & the P-Numbers
Two 50% activities make a 25% schedule, P50 vs P75, quarterly presentations, and taking the workshop to the contractors.
The Social Animal
“I’m from corporate, I’m here to help,” the soft skills the ISO docs don’t teach, and the two personalities to manage first.
Process Before Tool
The register is the point, Excel is fine, the platform that did everything, and the rollout that only worked after the training.
The History & Future of Risk
Against the Gods, animal sacrifice as risk mitigation, and AI as the super Monte Carlo that reads today’s data tomorrow.
The Advice Playbook
What the project director, the VP, the scheduler and the org each owe a new risk manager, and the insource question.
Takeaways, Books & Close
A lesson learned is a risk on a future project, change is the mother of all risk, the career path in, and the bookshelf.
Who carried the mic
Measured by words across the full transcript: one of the show’s more conversational splits. Orion’s longest turns are the “let me play it back for you as a layman” translations that turn a specialist’s discipline into a listener’s toolkit.
The Guest · Matt Mitchell
Matt started on the technical side: system administration at Deloitte’s consulting group, a trading-desk engineering seat at Enron Broadband (where he got his first formal risk training), then a decade across energy and enterprise software. The turn came at a software company with a serious risk management platform: rolling it out to customers taught him the ISO and PMI frameworks from the inside, and one of those customers, Noble Energy, hired him to run the system it had just bought. Eight years later he had been risk lead on some of the company’s largest capital projects, including Leviathan, and had built a risk champions program that carried the discipline across a global portfolio. Today he is building Electrical Grid Monitoring, a venture focused on innovative power line sensors.
“Risk is the effect of uncertainty on our objectives, where that uncertainty is a deviation from what we expected.”Matt Mitchell · the ISO definition, on the show, ~10:30
Career journey
Roles and years from Matt’s public LinkedIn profile. The software-to-risk turn is how he tells it on air (~1:10): a software company with “a really strong risk management platform,” then a move to one of its customers; Dyadem International is the risk-software stop his LinkedIn lists immediately before Noble Energy.
Credentials & the record
- Certification
- PMI-RMP: Risk Management Professional, Project Management Institute (per his LinkedIn; Orion introduces him as “a certified risk management professional”).
- Frameworks
- Teaches from ISO 31000, COSO ERM, PMI’s risk guidance and ISO Guide 73, the vocabulary standard he quotes for the definition of risk itself.
- Flagship
- Leviathan: offshore natural gas, eastern Mediterranean. He joined around 2015–16, right at final investment decision, and ran project execution risk from there (his telling, ~6:30).
- Now
- Electrical Grid Monitoring, “a new venture focused on innovative power line sensors” (the intro, ~0:40); Director of Customer Success per LinkedIn.
The toolkit
- Two registers
- Commercial and execution risk run separately on Leviathan, so the overlap didn’t “muddy the water” for the project team. (~8:35)
- Risk champions
- Interested people in every corner of the portfolio, trained, networked on a regular call, and left to run: “teach everyone that we could.” (~19:10)
- The cadence
- Risk reviews piggybacked on monthly cost and schedule reviews; Monte Carlo updated monthly, presented quarterly. (~29:15, ~37:50)
- Find him
- LinkedIn: /in/houstonmat
The Host · Orion Matthews
Orion is an award-winning programmer, entrepreneur and technology executive who has spent the last decade in the engine room of major capital projects. He founded Queryon in Washington, D.C. in 2015 with a focus on data analytics and software for the construction industry, starting with bellwether client BP, whose project-controls solutions his team deployed globally, from the North Sea to Azerbaijan to Houston. Today he's a recognized expert in PMO data analytics and project-controls reporting, serving billion-dollar portfolios for owners including BP, Santos, Balfour Beatty and Turner & Townsend, a regular speaker at major industry conferences on AI and analytics in capital projects, and the host of this show.
Why this pairing works
- Same problem
- Orion builds the project-controls reporting where, as he observes on air, risk is the one discipline still managed “from small to really large enterprises in Excel.” Matt spent a career moving it out of Excel, and then argues for moving the workshop view right back in. The tension is the episode.
- The translator
- Orion’s “let me play it back for you as a layman” passes (the time-horizon frame, the super Monte Carlo, the tax-man buckets) are the connective tissue that turns a niche discipline into something any project person can carry out of the room.
Beyond the PMO
- The builder’s arc
- Founded Introspect Software out of high school; built and sold Design-PT (acquired 2015). His software has run from McMurdo Station to aircraft carriers, with write-ups in Scientific American, CNN and Maxim, and a BP Helios Award.
- The Excel observation that frames the whole hour: “risk is probably the one area that I’ve seen more often than not managed, from small to really large enterprises, in Excel.” ~2:05
- The time-machine playback: “if we’re at time T zero and you pick a point out here at T 10… risk is saying, what is the actual deviation from expected.” ~13:20
- The witch-hunt question nobody asks out loud: “sometimes risk turns into a witch hunt, and people don’t wanna be the one to kick off the hunt.” ~30:50
- The super Monte Carlo: an LLM “running it against trillions of connected points to suss out probabilistic outcomes.” ~53:40
From Software to Risk Lead
Orion opens with the show’s standing frame and the guest’s résumé in one breath: a certified risk management professional, over a decade in risk and project controls across energy and industrial sectors, Noble Energy, and now a grid-sensor venture. Then the origin story, and it’s an unusual one: risk found Matt through software.
“As we rolled out this global risk management system, they realized they didn’t have anybody to manage it, and so that became my role… took on the role of risk lead and ended up with some of the very large projects that they had.”Matt Mitchell · ~1:40
The frameworks were the on-ramp
“With risk management, we have some pretty good guidance out there: ISO 31000, we’ve got Project Management Institute, that all kind of lay out this framework of what you should be doing… what I had to do was learn what the risk management process was from those frameworks’ perspective and then implement it for various companies.” ~2:30
The Excel problem
Orion’s framing from the reporting side: “risk is probably the one area that I’ve seen more often than not managed, from small to really large enterprises, in Excel.” Which makes a guest who arrived via risk software a rare specimen. ~2:05
- The first exposure: “First, I worked at Enron, and we had some formal training around risk management.” ~1:15
- The software company with “a really strong risk management platform,” rolled out to customers, prospecting what a global risk management system would do. ~1:25
- The verdict on the path: “Yes, it’s very much a niche, but it was kind of a natural fit.” ~2:55
Leviathan & the Two Registers
Public information only, by agreement: Leviathan, the giant natural gas field far offshore Israel, one of the largest offshore gas developments in the Mediterranean. Matt walks the concept history (a floating production vessel batted around for years, then a very large platform closer in, after Tamar proved the model), the sanction he intersected, and the register decision that made a megaproject’s risk manageable: split the commercial from the execution.
“This was such a large project, it had so many aspects of it. We eventually ended up running two different risk registers, because we had so much that was on the commercial side of things, and then there was the project execution… The overlap of those kind of muddies the water a little too much for the project team.”Matt Mitchell · ~8:35
Decades in the making
“These projects are decades in the making in some cases. And you have people on and off, and on and off, and a lot of knowledge gaps here and there… the capturing of that information and the risks that we considered and the reasons why we made certain decisions that we made, those should be documented, and documented well.” ~3:45
Even cancellation is a chapter
“Risk management is a key part of the entire life cycle of the project, even up until the point where the project might get canceled. Somebody might pick it up again five years down the road, and it’s gonna be important to understand what took place.” ~4:50
- The concept arc: “It started off as a floating production, FPSO, basically a ship… then ultimately, based on some of the successes of the other two platforms that had been put in, it became a very large platform a little closer in. And that was the final investment decision.” ~5:30
- Where he intersected it: “I got into that project around the 2015 timeframe, ’15 or ’16… right around the time that they made final investment decision and sanctioned that project as that large platform. Massive platform, in fact.” ~6:30
- Inheriting the register: “Let’s take that risk register and we’ll repurpose it… Some of these apply, some of these don’t.” The more mature the process, the easier the handoff. ~8:10
- The commercial side, illustrated: “It’s public information that they’re selling gas to Egypt, right?… that was one of the things we had to consider as part of all the commercial risk, but that’s not a project execution item.” ~9:30
- Orion’s read: geopolitical risk is almost a different discipline than engineering risk, “which maybe is a little bit more quantitative.” Matt: “Yes.” ~9:50
“I believe at FID, it was about 3.8 or 3.9, something like that. And I believe it came in right around there.” (~6:55) The sanction figure and the 2014–16 concept-to-FID timeline are Matt’s on-air recollections of a project he left years ago: treat both as directional.
Risk 101: Deviation from Expected
Orion asks for the 101, “a refresher even for the advanced project people.” Matt gives the textbook definition, boils a project’s objectives down to cost and schedule, defends the COSO view that overshooting your target is a risk too, and then spends the back half on calibration: the valve test, and the line that separates a real risk from a black swan.
“Risk is the effect of uncertainty on our objectives, where that uncertainty is a deviation from what we expected… identify what things could happen to prevent us from achieving those objectives. Or if something bad were to happen, what would we do to get it back on track.”Matt Mitchell · the ISO definition · ~10:30
Over is a risk too
“I kind of prefer the COSO perspective because it makes you think, if I come over, 150, can my production handle it? We’re actually seeing some instances where it couldn’t… it flooded the whole system and they had to redesign.” ~12:45
The valve test
An engineer swears valve failure is “an extremely high likelihood… very high. Very high.” Matt asks one question: “If you ordered 100 valves, how many of them would you expect to fail?” “Probably three.” “Okay, that’s a very low probability… so we put it in at very low in the risk register.” ~15:05
- Focus the objectives: “it’s most effective to boil those things down into what’s the effect on the schedule, what’s the effect on the cost,” because HSE-style objectives, while real, “muddy the water.” ~11:20
- Orion’s playback: risk always has a time horizon and an observer’s frame: T zero, a point out at T 10, and a mechanism that says “this should be here.” ~13:20
- The two biases you meet in every room: “Oh, yeah, that’ll never happen, we’ve never seen that,” and “we need to order 12 extra valves because we’re gonna have so many fail.” ~14:20
- Black swans have a Latin name: “de minimis… it’s so outrageous that we shouldn’t even consider it, because there’s nothing we could do about it if it occurred.” ~15:55
- The economics in one word: “You have to focus on what you can control and what reasonably will impact the project… otherwise we’re gonna waste a lot of money and waste a lot of time thinking about things like planes crashing.” ~16:10
Making Risk Economical
Orion plays the skeptical executive: the risks will probably occur anyhow, so what stops risk management from spending millions to prevent the one-in-a-million? Matt’s answer has two parts: a matrix denominated in this project’s money and time, and a training program that scales one risk manager across an entire portfolio.
“The company might have a global risk matrix or a corporate risk matrix, but the project has to have its own.”Matt Mitchell · ~17:45
The frame of reference
“A big risk on a million-dollar project might be $100,000, but… $100,000 risk on a billion-dollar project has a different frame of reference. The risk matrix is the important way to differentiate big risks on different projects.” ~18:15
The risk champions
“We used the term risk champions… people who kind of understood and had an interest in knowing more about what project risk management looked like, that we could go out and teach them and then let them go do.” A regular champions call kept them feeding off each other. ~19:10
- Scale the matrix to the budget: does a 100% impact mean 10%, 25%, 50% of this project’s cost? “That lets you frame that project in terms of its biggest risks and compare it to other projects of similar sizes.” ~18:00
- Why champions work: “It’s hard to do it all as a single individual, and risk management is all about everybody understanding how the whole process works. So we just tried to teach everyone that we could.” The audience: project controls, engineers, a lot of coordinators. ~20:10
- Orion’s safety-culture parallel: you don’t get safe execution by hiring one great safety manager; you build a culture. Matt’s version for risk: just start. ~20:45
Inside the Risk Workshop
Asked for the story of Leviathan’s first risk workshop, Matt grins: “I’d rather tell you the best way to do it… but I’ll tell you what we did instead.” The first one was awkward, because first ones always are. What follows is the real craft: managing personalities, eliciting risk from the quiet experts, respecting the field’s time, and never, ever starting from a blank screen.
“The leader of the entire group said, ‘You guys are here today to tell me why X is our biggest risk.’ Conducted the workshop. Everybody had their input, and X came out as the third-biggest risk from that group.”Matt Mitchell · ~24:50
Elicit the quiet ones
“Not only do you have to manage the loud personalities, but you have to coach the quiet ones as well… the term they use is elicit risk. Get them to tell you what is it that they’re thinking… and present it back to them: are you saying that this could occur?” ~23:15
The blank screen
“If you start off the meeting with all those personalities in the room and you got a blank screen and you say, ‘Okay, what are the risks?’ You’re destined to fail. We wanna have as much work done upfront as you can.” ~26:45
- Half the job is the room: “you have a lot of vocal voices… yes, let’s put that in the parking lot, we’ll take that offline… It’s a lot of personality management, especially initially.” ~22:20
- The field experts “are necessarily there, but they don’t wanna be there… you have to be considerate of their time, do as much homework and upfront work as you can to make that meeting valuable the whole time they’re there.” ~24:10
- The prep stack: a lessons-learned review, similar projects’ registers, and drive-by interviews (“hey, we’re doing a risk workshop, was wanting to get your perspective”), so you “come with something to show them.” ~26:20
- The doctrine behind it: “The PMI guidance is that a lesson learned is a future project risk.” ~27:20
- Never delete: “don’t delete a risk just because it’s mitigated or it’s no longer applicable, leave it in there and just say that it’s closed out, because somebody’s gonna need to review that sometime in the future.” ~27:50
The Flywheel & the Politics of Risk
How does a new risk manager on a billion-dollar job get the flywheel spinning? Piggyback the reviews that already exist, says Matt. Then Orion asks the harder question, the one that keeps registers empty: what do you do when raising a risk creates political problems for the person who raises it?
“The easiest way to dovetail a risk review in is to kind of piggyback on a cost or schedule review… They’re all related. And if you can listen in on a cost review, listen in on a schedule review, that will feed a lot of information into what goes into the risk register.”Matt Mitchell · ~29:15
Not a finger-pointing session
“At Noble, one thing that their drilling group did an excellent job of was, a lesson learned review is not a finger-pointing session, and so everything is on the table… we kind of piggybacked off of that in projects.” The no-blame lessons program is the political air cover for honest registers. ~31:15
The ancient jugs
“In the Mediterranean, we had a survey go through where one of the pipelines was supposed to be laid, and they found some ancient jugs on the sea floor… So they had to reroute the pipeline.” You do the survey for a reason, and you might carry some of those risks just in case. ~33:10
- The cadence: “typically it’s gonna be about a monthly type activity, just depending on the timeline of the project.” ~29:35
- Orion names the failure mode: it’s often easier to let a risk ride and shrug “hey, this happened” than to be the one who kicks off the witch hunt. ~30:50
- The private channel: “if you can have a one-on-one with somebody, you’re more likely to get something like that, and say, well, here’s how we’re gonna address it in the big group session.” ~31:50
- When the miss wasn’t on the register: “Those do happen, right? It’s the known unknowns versus the unknown unknowns… you do as much work upfront as you can to try to identify what types of those things might occur.” ~32:25
- The objectives filter, again: a piece of equipment a week late that doesn’t move the start-up date “might not be as big of a risk as it sounds.” ~33:45
Monte Carlo & the P-Numbers
“I always thought Monte Carlo was like a casino,” Orion offers, and gets the cleanest plain-language walkthrough of quantitative risk you’ll hear: compounding probabilities, a thousand iterations, and a company-level choice about how confident it wants to be. Plus the operating rhythm on Leviathan, and how risk crosses the corporate boundary to contractors.
“If you have an activity and you have a 50% chance of finishing on a day, and there’s a dependent activity that you have a 50% chance of finishing on time, you only have a 25% chance of meeting that schedule… that’s kind of what Monte Carlo is.”Matt Mitchell · ~34:40
P50 or P75 is a management decision
“It cycles through the thousand iterations and says, okay, you have a 50% chance of meeting this number or this date… The company has to make a determination whether they go with that 50% chance number, the P50 as we call it, or something more conservative like a P75: we have a 75% chance of coming in with this result.” ~35:30
Three inputs, or no output
“The inputs to a good Monte Carlo are an accurate updated budget or forecast, an accurate and updated schedule, and an accurate and updated risk register.” On Leviathan: “we would update the Monte Carlo every month, but we would only present it every quarter.” ~37:20
- Right-size the method: “Monte Carlo is most effective on large to very large projects… for smaller projects, we have the PERT method, the Program Evaluation Review Technique. That’s what I recommend for smaller projects.” ~36:30
- Who owns it: “The project manager, project director, they ultimately own all the risks… the risks should be individually owned by the people who are working to mitigate or close them out. But the project manager has final say.” ~38:30
- The risk lead’s quiet job: prepare the documentation the PM presents up the chain, and chase every risk owner for updates so the PM is never out of alignment. ~38:45
- Crossing the corporate boundary: “We would go directly to them, meet them at their office… could they bring whatever they were working from, whatever their risk registers were. And if we found deficiencies, we would just coach them.” ~39:40
- The good news about big contractors: “most of our big contractors like that did have a risk management function, and they were willing to meet with us.” ~40:10
Process Before Tool
Orion’s standing rule is “process before tool,” and Matt, the man who sold risk software for a living, agrees in the strongest possible form: the tool is far down the list; the register is the list. Excel is fine. The fancy platform earns its keep only if it can produce a view simple enough for the room.
“To go back to one is greater than zero: having a risk register is infinitely better than not having one at all… somewhere far down the list is the what tool do you use? But the top of the list is create a risk register. That’s it.”Matt Mitchell · ~44:45
Keep the workshop simple
“The main thing is to keep it simple, especially for risk reviews and especially for the project teams and the leads… a fancy, complex tool sitting around a workshop is a big waste of their time, and they’ll see it as that.” ~45:20
The platform that worked
The best tool he used “did all of those methodologies in one single platform… we actually ended up using it and kind of customizing it a little bit to make it super simple for project risk registers,” then exporting a few fields for the actual review. ~46:45
- What a project register is not: “failure mode effects analysis, security vulnerability analysis, pick one, HAZOPs, HAZIDs. Those are very specific and very detailed and very engineering-oriented, and they are not suited for project risk registers.” ~45:55
- The category definition: “The project risk register is the simplest form of risk review that exists. It’s very basic, focused on project objectives.” ~46:20
- Export or die: “if you choose too complex of a tool and it’s too difficult to do that export and review… it just won’t get done, and it won’t get updated, and you’ll have bad data in there.” ~47:30
- The enterprise reality: “could we get an entire project team to go into a tool and put risks in? No, absolutely not. But having those point contacts, risk champions, people who understood the process out in the field, that was very valuable.” ~48:20
The History & Future of Risk
Zoom all the way out: humans have been managing risk for tens of thousands of years, animal sacrifice included, and the discipline’s best book is a history. Then all the way forward: Matt’s bet that AI reads today’s risk data tomorrow, Orion’s “super Monte Carlo” frame, and the honest caveats about what the models can’t replace.
“One of the things that I say is that the AI that we’re using in 5 years or 10 years is going to be reading the data from today… where risk management is going is leaning on AI to help us figure out what we need to be doing to avoid risks, not only in the project world, but broadly.”Matt Mitchell · ~51:45
The risk-management mindset
“The lifecycle of a jet, it’s like 25 years for passenger service, after which it’s only for cargo. That’s a risk mitigation… you have a different perspective on life when you think of it from a risk management aspect.” ~50:20
A super Monte Carlo
“I think Monte Carlo was maybe sort of a rudimentary early application of AI… I think AI will outpace Monte Carlo as an approach to the potential outcomes of a project.” Orion’s frame: an LLM runs your tokenized register against trillions of connected points. ~52:50
- The bookshelf headline: Against the Gods: The Remarkable Story of Risk: “the early philosophers… loved to gamble because they understood what the odds were.” ~50:45
- Risk mitigation, Bronze Age edition: “in early civilizations, the sacrifice of animals was what was perceived to be a risk mitigation of fertility or crops or who knows what.” ~51:10
- Why AI beats the classic engine: “Monte Carlo is very dependent on the quality of the inputs, whereas with AI I feel like you can be a little softer on that quality and still have a good outcome… it’s easier to look across other projects with an LLM.” ~54:30
- The caveat for the haters’ row: “I still think for a lot of project scope you have to have the expert opinions. AI can do a lot, but you need people who have the experience and have been through it.” ~55:10
- Asked if robots are 50 to 100 years out, he shrugs: “who knows what the future holds… just the last couple of years of technology, seems like we’ve made some pretty big leaps.” ~55:50
The Advice Playbook
Orion runs the wrap-up as a role-play, one seat at a time: the project director who just hired a risk manager, the VP trying to smell trouble from the top, the scheduler who wants to be useful, and the org deciding whether to insource the function at all. Matt’s answers all rhyme: relationships early, plain language always.
“One of the main things that I encourage people to do is to describe risk in a way that it can be understood by someone who has nothing to do with the project.”Matt Mitchell · ~57:50
For the project director
“Make those connections, establish those relationships, get to know the leads of the various disciplines… give them the homework to go look at past projects and lessons learned… certainly develop those relationships as early as possible.” ~56:45
For the scheduler & cost engineer
“Always analyze inputs into your cost or your schedule with a little bit of skepticism, and ask questions to try to make sure that you as the scheduler or as the cost control person also buy into that result, and you know what the risks are, and you know that they have been identified and/or mitigated.” ~59:20
- The VP’s smoke test, in Orion’s playback: if the register is so technical you couldn’t hand it to an investor, “that’s probably a flag that you wanna take a harder look at risk.” Matt: “Correct… absolutely.” ~58:30
- Not just a number: “not just $10 million. We have to say what that risk is, and it has to be described in a way that is meaningful for outside parties.” ~58:15
- Insource or outsource: “I found it to be pretty effective to be insourced… certainly I have a little bit of a bias that I can recognize there.” If the org doesn’t understand risk yet, outsourcing can work, if the outsider still meets the key people. ~1:00:15
- The floor, either way: regular meetings, regular updates, “describing risk in a way that your organization can understand it, not just the risk manager… you can have success either way.” ~1:00:45
The Big Ideas
Three ideas carry the episode. Sketched here the way a risk lead would whiteboard them.
Leviathan’s risk load was too big for one list. The fix wasn’t a bigger list: it was a boundary, drawn at what the project team can actually control.
The commercial register
- Gas sales & offtake (Egypt)
- Geopolitics & markets
- Pipelines beyond the fence
- Managed separately, above the project
· drawn at FID ·
The execution register
- Schedule & cost impacts
- Engineering & delivery risk
- What the team can mitigate
- Reviewed monthly with the project
Gut likelihoods arrive miscalibrated from both ends of the spectrum. One reframing question converts feelings into frequencies before they hit the register.
His single takeaway, drawn as the cycle it is: a lesson learned is a risk on a future project, which means no register is ever really finished, and none should ever start blank.
Takeaways, the Bookshelf & the Links
The close runs from a Navy training slide to the philosophy of gambling Greeks, through the standards shelf (PMI, ISO 31000, ISO Guide 73, COSO), and out on how a student actually gets the job. Every recommendation from the episode, in his own words, plus all the links.
“Another one that I found in an old Navy training slide deck was: change is the mother of all risk… a lot of times when you have bad outcomes, it can be traced back to some kind of a change or a decision or something that we did differently than we had originally planned… anytime there’s any talk of change, that should be a risk conversation.”Matt Mitchell · ~1:02:30
Matt’s bookshelf, in his own words
- The book
- Against the Gods: The Remarkable Story of Risk · Peter L. Bernstein. “It talks about some of the early philosophers and how they loved to gamble because they understood what the odds were… It’s a fascinating book. It’s a great read, and it’s pretty cheap on Amazon.” (~50:45)
- Start here
- Project Management Institute risk guidance. “The Project Management Institute guidance on risk management is really good… it’s good guidance and it’s specific to projects. So that’s kind of where I would start.” (~1:07:10)
- The framework
- ISO 31000. “That is a framework and it’s more geared toward corporate-type risk management implementation… there’s a process that should be followed.” (~1:07:40) Same read on COSO ERM, whose over-and-under view of objectives he prefers (~12:45).
- The vocabulary
- ISO Guide 73. “It’s all of the definitions of terms around risk management. The one I gave about the definition of risk, that’s from the ISO Guide.” (~1:08:05)
- The conference
- IPA (Independent Project Analysis). “They do a lot of project-specific focus on risks. So any kind of IPA conference you can attend, I would encourage.” (~1:08:45)
The episode
- Watch
- Watch on YouTube · @TheMajorProjectPodcast
- Listen
- Apple Podcasts · Spotify
- The guest
- Matt Mitchell on LinkedIn
- The host
- Orion Matthews on LinkedIn · Queryon
- The show
- themajorprojectpodcast.com · new conversations from the people building projects over US$1 billion.
- The Bookshelf
- The Major Project Bookshelf · every recommendation from every episode, with the reasoning in the speakers’ own words.
- The jobs exist: “there are jobs open currently for project risk managers… typically it’s within like an EPC-type company, and they’re working across multiple projects.” ~1:04:15
- The usual door is sideways: “it’s sometime easier to move into that role once you’re within a company and are working on a project… it’s kind of how I found myself there.” ~1:04:40
- The profile that fits: “the very curious. Someone who’s very curious and loves to always be learning, because every project is different… What is different about this project? What risks might I have? What have I not thought of yet?” ~1:05:40
- The scale of the seat: “a project manager might work on three projects in their career… a risk manager, you are likely going to work on dozens of projects.” ~1:06:30
- The last tip: settle the language. “Settle on a set of definitions… like severity or impact, those kind of mean the same thing in risk management terminology. But just define what all those terms are for your project and for your program.” ~1:09:25
Highlights at a glance
Three moments to start with
- The two registers ~8:35
- The valve test ~15:05
- “I’m from corporate” ~41:10
If you run project controls
- The project-specific matrix ~17:45
- Piggyback the reviews ~29:15
- Monte Carlo’s three inputs ~37:20
The late-episode gold
- Describe risk for outsiders ~57:50
- A lesson learned is a future risk ~1:01:40
- Change is the mother of all risk ~1:02:30
Banner photos show the Leviathan production platform in the eastern Mediterranean, the project discussed in this episode: the gas-processing platform, photographed October 28, 2019 by Amir.bendavid, and installation of the platform’s topsides by the crane vessel Sleipnir, photographed from Ramat HaNadiv on September 17, 2019 by Deror Avi. Both via Wikimedia Commons, licensed CC BY-SA 4.0.
Quote Bank
The best on-the-record lines, gathered in one filterable place. “Highlight” marks the lines most worth scrubbing back for; quotes are lightly condensed and timestamps are approximate.
From Software to Risk Lead 0:00–3:00
- Highlight“As we rolled out this global risk management system, they realized they didn’t have anybody to manage it, and so that became my role… took on the role of risk lead and ended up with some of the very large projects that they had.”
- “With risk management, we have some pretty good guidance out there: ISO 31000, we’ve got Project Management Institute, that all kind of lay out this framework of what you should be doing.”
- “Risk is probably the one area that I’ve seen more often than not managed, from small to really large enterprises, in Excel.”
Leviathan & the Two Registers ~3:00–10:00
- “These projects are decades in the making in some cases. And you have people on and off, and on and off, and a lot of knowledge gaps here and there.”
- Highlight“The capturing of that information and the risks that we considered and the reasons why we made certain decisions that we made, those should be documented, and documented well. And risk management is one of the best ways to do that.”
- “Risk management is a key part of the entire life cycle of the project, even up until the point where the project might get canceled. Somebody might pick it up again five years down the road.”
- Highlight“We eventually ended up running two different risk registers… The overlap of those kind of muddies the water a little too much for the project team, so we just really wanted to focus on project execution.”
- “It’s public information that they’re selling gas to Egypt, right?… that was one of the things we had to consider as part of all the commercial risk, but that’s not a project execution item.”
Risk 101: Deviation from Expected ~10:00–17:00
- Highlight“Risk is the effect of uncertainty on our objectives, where that uncertainty is a deviation from what we expected.”
- “It’s most effective to boil those things down into what’s the effect on the schedule, what’s the effect on the cost.”
- “I kind of prefer the COSO perspective because it makes you think, if I come over, 150, can my production handle it? We’re actually seeing some instances where it couldn’t… it flooded the whole system and they had to redesign.”
- Highlight“I said, okay, well, if you ordered 100 valves, how many of them would you expect to fail? ‘Probably three.’ Okay, that’s a very low probability of that failure occurring, so we put it in at very low in the risk register.”
- “The Latin term is de minimis… it’s so outrageous that we shouldn’t even consider it, because there’s nothing we could do about it if it occurred.”
- “You have to focus on what you can control and what reasonably will impact the project… otherwise we’re gonna waste a lot of money and waste a lot of time thinking about things like planes crashing.”
Making Risk Economical ~17:00–21:00
- Highlight“The company might have a global risk matrix or a corporate risk matrix, but the project has to have its own.”
- “A big risk on a million-dollar project might be $100,000, but… $100,000 risk on a billion-dollar project has a different frame of reference.”
- “We used the term risk champions… people who kind of understood and had an interest in knowing more about what project risk management looked like, that we could go out and teach them and then let them go do.”
- “It’s hard to do it all as a single individual, and risk management is all about everybody understanding how the whole process works.”
- Highlight“One is greater than zero. It’s just about getting in there and doing it. Get in and start a risk register and begin working through what that whole process looks like.”
Inside the Risk Workshop ~21:00–28:00
- “The first risk workshop is the hardest, and after that it starts to become a little bit more mechanical, and people know what they’re expected to do.”
- “I’d rather tell you the best way to do it… but I’ll tell you what we did instead.”
- “That’s half the role, is being able to kind of manage those personalities… It’s a lot of personality management, especially initially.”
- “Not only do you have to manage the loud personalities, but you have to coach the quiet ones as well… the term they use is elicit risk.”
- Highlight“The leader of the entire group said, ‘You guys are here today to tell me why X is our biggest risk.’ Conducted the workshop. Everybody had their input, and X came out as the third-biggest risk from that group.”
- Highlight“If you start off the meeting with all those personalities in the room and you got a blank screen and you say, ‘Okay, what are the risks?’ You’re destined to fail.”
- “The PMI guidance is that a lesson learned is a future project risk.”
- “Don’t delete a risk just because it’s mitigated or it’s no longer applicable, leave it in there and just say that it’s closed out, because somebody’s gonna need to review that sometime in the future.”
The Flywheel & the Politics of Risk ~28:00–34:00
- Highlight“The easiest way to dovetail a risk review in is to kind of piggyback on a cost or schedule review… They’re all related.”
- “It feels like sometimes risk turns into a witch hunt, and people don’t wanna be the one to kick off the hunt, so to speak.”
- Highlight“A lesson learned review is not a finger-pointing session, and so everything is on the table.”
- “Yes, we’re finding faults and things, but this is good because we’re gonna prevent it from occurring again.”
- “Those do happen, right? It’s the known unknowns versus the unknown unknowns.”
- “They found some ancient jugs on the sea floor… So they had to reroute the pipeline. Those kinds of things happen, and it’s not every day that you’re gonna… find an artifact like that.”
- “We could have a delay… a piece of equipment arriving, but it doesn’t impact the schedule… it doesn’t impact the objectives of the project, so it might not be as big of a risk as it sounds.”
Monte Carlo & the P-Numbers ~34:00–40:00
- Highlight“If you have an activity and you have a 50% chance of finishing on a day, and there’s a dependent activity that you have a 50% chance of finishing on time, you only have a 25% chance of meeting that schedule.”
- “The company has to make a determination whether they go with that 50% chance number, the P50 as we call it, or something more conservative like a P75.”
- “Monte Carlo is most effective on large to very large projects… for smaller projects, we have the PERT method, the Program Evaluation Review Technique.”
- Highlight“The inputs to a good Monte Carlo are an accurate updated budget or forecast, an accurate and updated schedule, and an accurate and updated risk register.”
- “We would update the Monte Carlo every month, but we would only present it every quarter.”
- “The project manager, project director, they ultimately own all the risks… the risks should be individually owned by the people who are working to mitigate or close them out.”
- “We would go directly to them, meet them at their office… and if we found deficiencies, we would just coach them and work with them to get them to do things the way that we preferred.”
The Social Animal ~40:00–44:00
- Highlight“My favorite icebreaker is, you show up for a first meeting and say, ‘I’m from corporate. I’m here to help.’ And you always get a bunch of laughter.”
- “They’re not in the ISO docs, and there’s not a lot of very specific guidance in those frameworks… just get started, get going. It gets easier as you go.”
- “It’s one end of the spectrum or the other. It’s the everything is bad and is going to happen, and you need to put 15 risks in your risk register for me, or none of that’ll never happen, so don’t even put it in there.”
- “You have to kinda talk them off the ledge… it’s not just about you, it’s about future projects.”
Process Before Tool ~44:00–49:00
- Highlight“Having a risk register is infinitely better than not having one at all… somewhere far down the list is the what tool do you use? But the top of the list is create a risk register. That’s it.”
- “A fancy, complex tool sitting around a workshop is a big waste of their time, and they’ll see it as that.”
- Highlight“The project risk register is the simplest form of risk review that exists. It’s very basic, focused on project objectives.”
- “If you choose too complex of a tool and it’s too difficult to do that export and review… it just won’t get done, and it won’t get updated, and you’ll have bad data in there.”
- “Could we get an entire project team to go into a tool and put risks in? No, absolutely not. But having those point contacts, risk champions, people who understood the process out in the field, that was very valuable.”
The History & Future of Risk ~49:00–56:00
- “The lifecycle of a jet, it’s like 25 years for passenger service, after which it’s only for cargo. That’s a risk mitigation… you have a different perspective on life when you think of it from a risk management aspect.”
- “It talks about some of the early philosophers and how they loved to gamble because they understood what the odds were… It’s a fascinating book.”
- Highlight“The AI that we’re using in 5 years or 10 years is going to be reading the data from today.”
- Highlight“I think Monte Carlo was maybe sort of a rudimentary early application of AI… I think AI will outpace Monte Carlo as an approach to the potential outcomes of a project.”
- “It really does seem like, yeah, maybe it is like a super Monte Carlo in a way.”
- “I still think for a lot of project scope you have to have the expert opinions. AI can do a lot, but you need people who have the experience and have been through it.”
The Advice Playbook ~56:00–1:01:00
- “Give them the homework to go look at past projects and lessons learned… certainly develop those relationships as early as possible.”
- Highlight“Describe risk in a way that it can be understood by someone who has nothing to do with the project.”
- “Not just $10 million. We have to say what that risk is, and it has to be described in a way that is meaningful for outside parties.”
- “Always analyze inputs into your cost or your schedule with a little bit of skepticism, and ask questions.”
- “I found it to be pretty effective to be insourced… certainly I have a little bit of a bias that I can recognize there… you can have success either way.”
Takeaways, Books & Close ~1:01:00–1:10:30
- Highlight“A lesson learned is a risk on a future project… even an old risk register is a lessons learned register, right? You’ve captured a number of lessons learned there.”
- Highlight“Another one that I found in an old Navy training slide deck was: change is the mother of all risk… anytime there’s any talk of change, that should be a risk conversation.”
- “Project risk management is the simplest form of risk methodologies that exists… the simpler you approach it, the more success you’ll have and the easier it will be to replicate that success over time.”
- “The very curious. Someone who’s very curious and loves to always be learning, because every project is different.”
- “A project manager might work on three projects in their career… a risk manager, you are likely going to work on dozens of projects.”
- “Settle on a set of definitions, and just know that people will have experienced other terms that meant the same thing.”
The Social Animal
“So the risk manager is kind of a social animal, would you say?” “Right. Lots of meetings.” Orion’s three buckets (is this person helping me, draining my time, or going to get me?) set up the disarm move, the soft-skill path the ISO documents never mention, and the two personalities you learn to manage first.
Not in the ISO docs
“They’re not in the ISO docs, and there’s not a lot of very specific guidance in those frameworks… honestly, I think it’s just a matter of getting your feet wet… So just get started, get going. It gets easier as you go.” ~42:15
The two ledges
“It’s one end of the spectrum or the other. It’s the everything is bad and is going to happen, and you need to put 15 risks in your risk register for me, or none of that’ll never happen, so don’t even put it in there.” ~42:50