The Major Project Podcast · Episode Brief · 002

Greening Riyadh: Inside Saudi Arabia’s $10 Billion Urban Oasis

What does it take to grow 7.5 million trees across a capital city? Jovita Stander (project controls director on Green Riyadh, now with Knight Frank) on running the reporting hub of a city-wide megaprogram, and why the basics beat the dashboards.

Jovita Stander Jovita StanderGuest · Project Controls Director
Orion Matthews Orion MatthewsHost · Founder, Queryon
Released Oct 14, 2025 Main episode · 1h 10m Green Riyadh · US$10B+ program 7.5M trees
Wadi Hanifah, Riyadh, 2010–11 · P. Dowley, S. Six & Dainomite · CC BY 2.0 / CC BY-SA 3.0
Jump in Watch on YouTube Listen · Apple Podcasts Spotify
More ways to listen
Full transcript All episodes
Share: LinkedIn X
The Conversation

Episode Overview

Most people hear “billion-dollar project” and picture steel and concrete. Episode 002 is about planting trees: 7.5 million of them, across an entire desert capital. Jovita Stander ran project controls on Green Riyadh, the Vision 2030 megaprogram turning Riyadh into an urban oasis, and she walks Orion through the whole machine: the KPIs behind the trees, the 1,300 km treated-wastewater irrigation network, the Primavera P6 ↔ ArcGIS backbone that keeps a city-wide scope honest, and the leadership it takes to run the numbers when you’re the only woman in the boardroom.

71
Minutes on the record
12,994
Words in the transcript
56
Speaker turns in the transcript
83%
Guest share of words spoken
The thesis

Order to chaos, then the tools

“I bring order to chaos, and project controls does a lot of that.” Before AI, PMIS or dashboards: cutoff dates, a project calendar, a golden thread through your reports. Garbage in, garbage out.

The guest

A project-controls passport

Six countries, six sectors: from South Africa via Brazil and Texas midstream to Riyadh. Project Controls Director on Green Riyadh; today with global real-estate consultancy Knight Frank.

The project

Green Riyadh

A Vision 2030 urban-afforestation program: 7.5M native trees, ~1,300 km of treated-sewage-effluent irrigation, a 1–2°C cooler city, cleaner air, and a park within 300 m of every neighborhood.

About this brief

Quotes are transcribed from the released episode and lightly condensed for readability: fillers and false starts removed, meaning untouched; timestamps follow the published cut and are approximate. The chapter map and the statistics above are computed from the full transcript. Biographical details come only from what Jovita says on the record and the episode’s public pages; she speaks in a personal capacity, and her views are her own. Program figures cited on air (budgets, populations, KPI targets) are as she recalled them in conversation. Treat them as directional. Banner photos: Wadi Hanifah, Riyadh · Wikimedia Commons, open-licensed (full credits below).

As Recorded

Episode Timeline

The conversation as it unfolded: eight chapters across 71 minutes, following the show’s four-act arc: intro, the project, advice, wrap-up. The strip maps each chapter’s share of the runtime; timestamps are approximate. Click any block to jump to its chapter.

The cold open

“What does it take to grow 7.5 million trees across the capital city? We’re welcoming Jovita Stander to the podcast for an inside look at Green Riyadh, a $10 billion megaproject that is set to transform the capital city of Saudi Arabia into a green oasis.” · Orion, 0:11

0:006 min01

Vision 2030 & the Path to Riyadh

The welcome, the initiative behind the project, and a career that runs through six countries.

6:1210 min02

Anatomy of a $10B Urban Forest

City numbers, the KPIs behind the trees, and irrigation from the city’s own wastewater.

16:239 min03

A Program, Not a Project

The call from Riyadh, smart parks with stadiums, staggered priorities, and what her team looked like.

25:097 min04

Where the Schedule Meets the Map

P6 and ArcGIS speaking the same location codes, and 72 native species for 7.5M trees.

32:107 min05

Leading in a Sea of Men

The only senior woman on the program: kindness first, firmness when it counts, and the human element.

38:516 min06

High-Stakes Rooms

Presenting to His Excellency: color-coded notes, candor over fudging, and practicing out loud.

44:5110 min07

The Basics Before the Dashboards

Cutoff dates, the golden thread, gut-check QC: the routine that makes megaproject data trustworthy.

54:3816 min08

Careers, Women & Mentors

Vertical vs horizontal career streams, advice for women entering the field, and the mentorship habit.

Who carried the mic

Jovita Stander · ~59 min · ~10,800 words (guest) Orion Matthews · ~12 min · ~2,100 words (host)

A strongly guest-forward split: Orion sets up the runway, Jovita flies. Word counts measured across the full transcript.

The Guest

The Guest · Jovita Stander

Jovita Stander
Jovita Stander
Project Controls Director, Knight Frank · formerly Project Controls Director, Green Riyadh
Riyadh, Saudi Arabia
Project ControlsProgram ReportingP6 × GISMegaproject LeadershipGlobal Career

Jovita is a South African project-controls leader whose career has run through six countries and six sectors: urban forestation, mixed-use high-rise, transportation and rail infrastructure, power, oil & gas export terminals, and mining, with stops in South Africa, Angola, Mozambique, Brazil and five years in the United States. The road there is its own story: nearly eight years leading IT projects for Vodacom, a Centurion coffee shop she owned and ran, then a decade on African megaprojects: planner roles on Mozambique’s Matola coal export terminal and Benga CHPP, then operations manager at South Africa’s ~$9B Medupi power station, before five years with WSP in the US, rising from a ~$2B grid-reliability program in Maine to Vice President, Project Controls in Houston. She was sitting at home in the Houston area in 2023 when a call came out of the blue: Green Riyadh needed a project controls director. She researched the program, took the job, and (with Egis) led a 24-person controls team at the reporting hub of a $10–11 billion urban-afforestation megaprogram. Since late 2024 she has been Director of Project Controls with Knight Frank, the global real-estate consultancy, based in Riyadh.

“I’m really a problem solver. I bring order to chaos. And I think project controls does a lot of that: it brings order to chaos.”Jovita Stander · on the show, ~4:45
6
Countries worked, on four continents
6
Sectors: forestation to mining
5
Years in the US before the Riyadh call
$10–11B
Green Riyadh budget when she joined (2023, as cited)

Career journey

IT projects & own business
Planning · mining, rail & power
Project controls · US
Program controls · Riyadh
South Africa · Angola
Mozambique & South Africa
United States
Saudi Arabia
01ExponantProject Leader, Vodacom IT1998–2006 · Midrand, SA
02ButterfieldOwner-Manager, coffee shop2006–2008 · Centurion, SA
03ABC IT SolutionsProject Mgmt Team Leader2008 · Luanda, Angola
04ELB EngineeringSenior Project Planner2008–2010 · Matola Coal Terminal, Mozambique
05SedgmanProject Planner2010–2012 · CHPPs, Mozambique & SA
06WSP in AfricaProject Planner2012–2015 · SA & Mozambique
07WSP in AfricaOperations Manager2015–2018 · Medupi Power Station, ~$9B
08WSP USASenior Project Controls2018–2019 · Maine · AVANGRID, ~$2B
09WSP USADirector, Project Controls2019–2022 · Houston
10WSP USAVP, Project Controls2023 · Houston
11EgisDirector, Project Controls2023–2024 · Green Riyadh, ~$11B
12Knight Frank MENADirector, Project Controls2024– · Riyadh

Career map compiled from Jovita’s LinkedIn bio; spans rounded to the year.

The project-controls passport

Countries
South Africa (home: “please don’t confuse my accent with Australia”), Angola, Mozambique, Brazil, the United States, Saudi Arabia.
Sectors
Urban forestation · mixed-use high-rise · transportation & rail infrastructure · power · oil & gas export terminals · mining.
Education
MSc, Project Management in Construction, University of the Witwatersrand; business administration degree, Faculdade Dom Pedro II, Brazil; executive-leadership & change-management certificates, Cornell (2024–25).
Certifications
PMP® · PMI Scheduling Professional (PMI-SP)® · Earned Value Management · Quantitative Project Cost & Schedule Risk Analysis.
Self-portrait
“A gypsy at heart” who loves that projects end: “at one point this will come to an end, and I can move on to a new adventure.”

Now & on the program

Today
Project Controls Director with Knight Frank (MENA), the global real-estate consultancy. On the Riyadh core team since November 2024, leading the project-controls function across its KSA programs.
On Green Riyadh
With Egis (2023–24), ran a 24-person team spanning scheduling, cost, KPIs, QA/QC, document control and risk, plus the GIS team and a graphic-design team she says every project-controls group should have.
Find her
LinkedIn: /in/jovita-stander · “I’m probably the only one. Look me up; I’ll be happy to connect.” Her long-running blog: Planner’s Logbook.
In her own words

“Really I’m a gypsy at heart, so I can’t stay in the same place doing the same thing for a long time… I think I’ve chosen the right career, or it chose me, I don’t know.” ~5:05

The Host

The Host · Orion Matthews

Orion Matthews
Orion Matthews
Founder, Queryon · Host, The Major Project Podcast · PMO data & analytics
Eugene, Oregon, United States
Project Controls ReportingPMO Data AnalyticsCapital PortfoliosAI in ProjectsPower BI

Orion is an award-winning programmer, entrepreneur and technology executive who has spent the last decade in the engine room of major capital projects. He founded Queryon in Washington, D.C. in 2015 with a focus on data analytics and software for the construction industry, starting with bellwether client BP, whose project-controls solutions his team deployed globally, from the North Sea to Azerbaijan to Houston. Today he's a recognized expert in PMO data analytics and project-controls reporting, serving billion-dollar portfolios for owners including BP, Santos, Balfour Beatty and Turner & Townsend, a regular speaker at major industry conferences on AI and analytics in capital projects, and the host of this show.

Why this pairing works

Reporting is the product
Jovita ran the reporting hub of a $10B+ program; Orion builds the reporting machinery billion-dollar portfolios run on. The whole conversation lives at that intersection: cutoff dates, golden threads, dashboards last.
Data with a story
Her project-controls team included graphic designers; his bookshelf includes Storytelling with Data. Both land the same lesson: numbers only persuade when someone shapes them into a narrative.

Beyond the PMO

The builder’s arc
Founded Introspect Software out of high school; built and sold Design-PT (acquired 2015). His software has run from McMurdo Station to aircraft carriers, with write-ups in Scientific American, CNN and Maxim, and a BP Helios Award.
Chapter 01 · Act I · 0:00

Vision 2030 & the Path to Riyadh

Before the trees, the why. Green Riyadh is one project inside Saudi Arabia’s Vision 2030 (the 2016 initiative to diversify the economy away from oil), and Jovita opens with the goals the greenery actually serves: life expectancy up from 74 to 80, weekly exercise up from 13% to 40% of the population, three Saudi cities in the global top 100, and more Saudi women in the workforce. Then Orion rewinds to the guest herself: a South African “order-to-chaos” problem solver whose project-controls career has circled the globe.

“Part of Vision 2030, which is obviously close to my heart, is to increase the representation of Saudi women in the workforce.”Jovita Stander · ~2:00
Key moments
  1. Vision 2030, unpacked: launched in 2016 by the Crown Prince to diversify the economy. Green Riyadh is one of its many projects. ~0:48
  2. The health targets behind a tree-planting program: life expectancy 74 → 80, weekly exercise 13% → 40%, three cities in the world’s top 100. ~1:30
  3. Six countries, six sectors: South Africa, Angola, Mozambique, Brazil, the US, Saudi Arabia; forestation, high-rise, rail, power, export terminals, mining. ~3:15
  4. The self-portrait: a problem solver who brings order to chaos, loves that projects end: “a gypsy at heart.” ~4:45
Don’t miss The accent aside (~4:00): “Please don’t confuse my accent with Australia… how can you confuse our accents?” The moment the episode relaxes into itself.
Chapter 02 · Act II · 6:12

Anatomy of a $10B Urban Forest

Jovita builds the case bottom-up, the way a project controller would: city first, program second. Riyadh’s population (about 7 million in 2022) is forecast to hit 9.6 million by 2030, and the growth is exactly why the greening works: 100% of the irrigation comes from treated sewage effluent, so more residents literally means more water for trees. Launched in March 2019, Green Riyadh spans neighborhoods, parks, mosques, roads, schools and the wadis, with KPIs that go far beyond a tree count.

The city, in numbers (as cited)

≈7M people in 2022 → 9.6M forecast by 2030 (4.1M Saudis + 5.5M expats): “there’s probably no country that’s not represented here.” Roughly 38% growth, and ~305,000 new housing units expected between 2024 and 2034. ~7:00

Water from the city itself

“The irrigation will be done using treated sewage effluent… about 1,300 kilometres of irrigation network throughout the city; a hundred percent of the irrigation will be this type of water.” Sized off the population’s greywater output. ~10:45

Key moments
  1. The KPIs behind the trees: drop the city’s temperature 1–2°C, cut CO₂ 3–6%, absorb the winter rains, lift the look of a city of browns and beiges. ~12:30
  2. Rain in the desert: “When it rains, people are so happy they go out of the offices and film the rain. I just find that beautiful.” ~13:20
  3. Stormwater as scope: capture the November–January runoff, reuse it for irrigation, prevent the floods. ~13:45
  4. The livability standard: every neighborhood within 300 metres of a green space, to pull people outdoors. ~15:05
  5. Orion plays it back as three scopes: canopy, stormwater, parks & public space. Jovita confirms, and stacks the co-benefits. 15:22
“The natural landscape is tones of browns and light beige… the moment you see something green, it’s nice on the senses. It probably lifts your mood, at least it lifts mine.”Jovita Stander · ~14:30
Numbers worth noting

The population forecasts, growth rates, housing figures and KPI targets in this chapter are as Jovita cited them from memory on the show. A project controller’s recall is good, but treat them as directional rather than audited.

Chapter 03 · Act II · 16:23

A Program, Not a Project

The origin story and the org chart. Jovita was at home near Houston in 2023 when the call came out of the blue; by the time she landed, the budget stood, in her recollection, between $10 and $11 billion US. What she found wasn’t one project but a program of typologies: linear road corridors, whole neighborhoods, and parks built from scratch: “smart parks” with retail, walking routes, digital connectivity, metro links and, in some cases, a stadium inside the park.

“They talk about the Green Riyadh project, but in actual fact the project is a program… And the park is not just a park, it’s almost like a smart park. Some of the parks actually have a stadium.”Jovita Stander · ~18:30

Staggered on purpose

When she joined, a pilot batch of roads was nearing handover while other projects sat in design, tender or planning. “It was actually good that it was staggered… you can’t dig up the whole city for the network; it’ll just be one big chaos. We don’t talk about phases; we talk about priorities.” ~19:50

The team she ran

Planning & scheduling, cost (CPI and friends), document control, risk and reporting, plus the GIS team, and a graphic-design team producing the presentations and park brochures leadership needed. Permitting sat with stakeholder managers but lived on her schedule. ~21:00

Key moments
  1. The call: “I was actually sitting in my house in Katy, Houston, Texas, when I got a call out of the blue… I did a little bit of research, and I ended up here.” ~17:05
  2. Why typologies make it a program: roads are linear, neighborhoods are many, parks start from scratch, and not everything can start at once. ~18:00
  3. Her hot take: “Every project controls team should have the graphic design under them. I’m just going to say that.” ~22:30
  4. Orion raises Storytelling with Data: form over function fails; the story is what gets decisions made. Jovita: one page, one infographic, everybody understands. 22:43
  5. Permits in Saudi Arabia are strict (no excavation without an excavation permit), so permitting milestones live on the schedule even though the stakeholder team owns them. ~24:30
Worth pausing on The graphic-design confession (~22:30–24:10): a numbers director arguing that every project-controls team needs designers: “one picture is more valuable than a thousand words.” PMO leads, take note.
Chapter 04 · Act II · 25:09

Where the Schedule Meets the Map

The most technical stretch of the episode, and the one Orion came for. Green Riyadh runs on two databases (Primavera P6 for the schedule, ArcGIS for the city), and they’re joined by a shared coding system: every mosque, road segment and wadi parcel that gets a tree, shrub or ground cover carries a location code that lives in both systems, with costs attached. Change the scope on the map, and it reconciles in the schedule; update progress in P6, and it flows back to GIS.

“Each of those little assets had a code, and those codes would tie back into P6… so we could always relate back; it doesn’t matter which database you were using.”Jovita Stander · ~27:30

The Friday-mosque example

Neighborhood A has ten mosques to green. Scope changes to just the Friday mosque (the big one used for weekly prayers), and the change ripples cleanly: GIS codes out, P6 activities and costs adjust, progress flows back. ~28:40

GIS as a planning tool

Greening a wadi means knowing exactly which parcel is yours. GIS delineated the boundaries; where ownership was unclear, the GIS staff or stakeholder managers checked with the municipality before a single tree went in. ~30:00

Key moments
  1. The tree management office (alongside facility, construction and project management offices) owns the species strategy, backed by a long-standing local specialist firm with landscape engineers and GIS staff. ~29:30
  2. The palette: about 72 species native to the region (heat-resistant, low-water), “a lot of acacias, which are thorn trees; we get them a lot in South Africa… of course palm trees.” ~30:20
  3. The canopy trade: swap species (still native) and you can hit the same canopy-cover KPI with fewer trees: “instead of 7.5 million, it could be seven.” The KPI is shade, not the tree count. ~31:20
  4. At handover, every green asset maps back to GIS: the city gets a living inventory, not just an as-built. ~27:50
He brings receipts Orion’s follow-ups here (25:09, 29:01) are the PMO-data-guy questions: which tools, who owns the trees, how do two databases stay honest. If you integrate schedule and spatial data anywhere, this chapter is your blueprint.
Chapter 05 · Act II · 32:10

Leading in a Sea of Men

The chapter that gives the episode its heart. For the first time in her career, Jovita led an all-male team, and was the only senior woman on the program, presenting monthly to His Excellency the chairman. Some team members were open; others circumvented or ignored her. Her answer wasn’t to assert rank. It was kindness with a spine: work alongside the team through the all-nighters, feed them, recognize good work publicly, and put her foot down, with respect, when the debate was done.

“Standing in the boardroom, it was a sea of men in front of me… This really was the first time in my life that there was no other female in the boardroom.”Jovita Stander · ~33:00

Kindness, then firmness

“I had an option to assert my authority… or do it in a more subtle way. If you do it in a more pleasant way, you gain more in the long run. It might take longer, it did take me longer, but it was the right course.” And when needed: “We’ve now debated this; this is the direction.” ~34:40

The human element

Most of her team’s families were back home (India, Pakistan, Bangladesh, the Philippines), some seen once a year. “If there’s sickness or issues at home, they can’t be there… you need to take that human element into consideration.” Low productivity usually has a story. ~37:20

Key moments
  1. Last one out: “I would always be the last one going home. I would never leave before them and the work was finished.” ~36:10
  2. The sushi story: working through the night, dinner’s on her: “The one guy said, ‘I want sushi.’ I said, order it, no problem… They did it once, and they never ordered sushi again.” ~36:30
  3. Recognition as leadership currency: “A lot of them were not used to it… I think that buys you as a leader a lot of miles, and give the credit; don’t take it for yourself.” ~38:20
  4. Empathy for the other side of the table: it may have been the first time some of them reported to a woman: “I had to take that into consideration as well.” ~35:30
Don’t miss The full leadership run (~32:40–38:50): six unbroken minutes on earning authority you weren’t handed: bite your tongue, take a walk, come back kind, stay firm.
Chapter 06 · Act II · 38:51

High-Stakes Rooms

How do you walk into a monthly presentation to the program’s chairman (a room full of very senior people) and hold the floor? Jovita’s system is disarmingly analog: a printed deck covered in color-coded Post-it notes, data she already knows cold, a capable deputy on WhatsApp standby outside the room, and rehearsal out loud at home. And when a question lands that she can’t answer: say so, promise the follow-up, deliver it.

“I don’t have the answer for you now, Your Excellency, but I will get it to you as soon as we finish the meeting… I think you lose more credibility by trying to fudge it.”Jovita Stander · ~41:20

Her prep ritual

“You can never be prepared enough. Prepare.” Print the deck, annotate it with reminders in colors only she can decode, and practice the words out loud at home: “you need to feel confident with the data you are speaking.” ~39:30

The introvert’s edge

“I’m an introvert by nature… in the spotlight I’m not in my natural element, so I can’t think on my feet immediately. The nature of project controls is to deal in facts: if you say it’s 54%, it doesn’t mean it’s 52%; it’s 54%.” ~43:45

Key moments
  1. The opening joke that isn’t the advice: “First of all, fake it till you make it. No, I’m just joking.” The real tip follows immediately: over-prepare. ~39:25
  2. The WhatsApp lifeline: her project control manager on standby outside the room. Sometimes the chairman wanted the number before the meeting ended, and got it. ~42:10
  3. Orion’s riff: people rarely lie in project reporting. They weave, dodge and obfuscate, and it erodes credibility fast. “Being able to tell people what they don’t want to hear is a real skill.” 42:42
Don’t miss The candor exchange (42:42–44:50): Orion names the weave-and-dodge instinct, Jovita answers with the introvert’s case for verified facts over fast answers. The most transferable five minutes of the episode.
Chapter 07 · Act II · 44:51

The Basics Before the Dashboards

Orion asks how she QCs data she suspects is wrong, and Jovita delivers the episode’s thesis: it isn’t the tooling, it’s the basics. On Green Riyadh, every department reported to a different cutoff date until she spent two months of explaining, convincing and reinforcement to land a single project calendar. From there: sense-check the week-over-week movement, go back to the source when your gut nags, and make sure a “golden thread” runs from weekly reports into the monthly, quarterly and annual story.

“You need to start with the basics. And the basics is cutoff dates, so that everybody reports to the same cutoff date.”Jovita Stander · ~45:45

The gut-check QC

“If you’re jumping X percent in a week, does it make sense? … If something is nagging and you’ve got that gut feeling, even if you can’t put your finger on it, rather go back and check.” Sometimes just asking the source surfaces the extra digit. ~48:15

The golden thread

“Is there a golden thread through your weekly reports that feeds into your monthly report? If you deconstruct the month, will it talk to the third week, the second and the first?” If not, your data accuracy story has a hole. ~49:00

Key moments
  1. Orion’s analogy: learning to run isn’t about the shoe: “the basics are hard,” and everyone assumes project controls is advanced tooling and magic. 49:37
  2. Why AI waits: “Garbage in, garbage out… these wonderful tools will not help the decision makers make good decisions” if the inputs and processes underneath are wrong. ~50:50
  3. Routine as the discipline: “Project controls is all about routine: every month, in those 30 days, something has got to happen at certain points, and then next month you repeat it.” ~52:00
  4. The hub: a big project isn’t chaotic because people are lost: it’s moving parts everywhere, and “project controls is the hub in getting all this information together.” ~53:10
  5. Then, and only then: PMIS, dashboards, AI, “the goal is to be more efficient and provide accurate data in a very short amount of time.” ~54:00
Tape this to the war-room wall One project calendar. Common cutoff dates. Sense-check the deltas. Golden thread from weekly to yearly. Basics first, dashboards after: the whole chapter in five lines.
Chapter 08 · Acts III–IV · 54:38

Careers, Women & Mentors

The advice block runs long and earns it. For students eyeing the field: “go for it”, then a map of the career streams inside project controls, vertical mastery versus horizontal range. For women entering a male-dominated industry: the field is changing, your leadership style is an asset, and a thick skin is part of the kit. And for everyone, the closer: get yourself a mentor. She still does, decades in.

“You can become the subject-matter expert, the depths of knowledge in P6, or you can move horizontally into risk, cost, the commercial side, and then go up… It really gives you a lot of opportunity.”Jovita Stander · ~56:30
For starters

Go for it, and keep learning

“I’m an eternal learner, and in project controls you need to be that.” New industry? Do the homework: in Texas she taught herself midstream oil & gas, down to what a pumping jack is called. ~58:50

For women

Different, not wrong

“Women have a different way of leadership, of addressing problems… it’s not right or wrong, it’s just different.” Nordic countries are near 50/50; the rest of the industry is catching up. “I would encourage them to do it.” ~1:05:00

For everyone

Get a mentor. Still.

“Go to somebody that is already experienced and ask them: will you be my mentor?… When I ask for help, nobody has ever said no.” Discussing the problem makes the final decision better: that’s strength, not weakness. ~1:08:40

Key moments
  1. The short answer: “Go for it”, then the streams: scheduler, cost, risk, document control, commercial, reporting. ~55:15
  2. Orion’s conductor question: schedulers master a rigid, mathematical craft. How do you learn the convening skill that gets the band playing to one downbeat? 59:30
  3. Her answer: personality. The brilliant risk manager who lives for risk probably shouldn’t run the hub: “ask yourself: do I want many things at once, or one thing deep? And re-ask every five years.” ~1:02:30
  4. On thick skin: “You never need to apologize for being a woman in this field… but you cannot be easily offended.” A couple of times she “lost it a little bit”, and that sent a message too. ~1:06:20
  5. The benediction: “I’ve been very, very blessed in this career. If I had a choice, I would do it all over again.” ~1:07:15
  6. Wrap-up: find her on LinkedIn (“I’m probably the only one”), and Orion teases the career chart and links below the video. 1:07:51
Don’t miss The mentorship close (~1:08:00–1:10:20): the episode’s warmest stretch, and the single most actionable minute for anyone early in their career: just ask.
Concepts, Drawn Out

The Big Ideas

Three ideas carry the episode. Sketched here the way a program war room would whiteboard them.

1 · The schedule–map handshake

Two databases, one language: every green asset gets a location code that lives in both ArcGIS and Primavera P6 (with costs attached), so scope, schedule and money reconcile at street level, in either direction.

Mosques · Friday & weekly Road segments Parks & wadi parcels
Shared location codesArcGIS ↔ Primavera P6 · costs attached
One reconciled truthScope changes ripple both ways; at handover, every tree maps back to GIS.
From the conversation, ~25:28–31:20 · the Friday-mosque scope change is the worked example
2 · Basics before the dashboards

The shiny layer only works if the boring layer underneath is right. Jovita’s order of operations for any new program, and her caution for the AI era.

The boring layer (first)
  • One project calendar, common cutoff dates
  • Sense-check the week-over-week deltas
  • Gut nagging? Go back to the source
  • Golden thread: weekly → monthly → yearly
  • Routine, repeated every 30 days
The shiny layer (after)
  • PMIS platforms & dashboards
  • S-curves, infographics, storytelling
  • AI tooling: amplifier, not fixer
  • Faster, accurate data for decision makers
From the conversation, ~45:28–54:00 · “start with the basics… then go for the dashboards”
3 · Two ways up in project controls

Her career map for newcomers: depth and breadth are both winning strategies. The trap is taking the hub seat with a specialist’s habits. Ask yourself which fits your personality, and re-ask every five years.

← one discipline, deep · many disciplines, wide →
The subject-matter expert

Vertical mastery: the P6 planner everyone calls. “We do need people like that… the depths of knowledge.”

The horizontal mover

Scheduler → risk → cost → commercial. Each move widens the base before the next climb.

The trap

Stepping into the director seat still in love with one discipline: the band never gets its downbeat, and you end up managing chaos.

The hub: PC director

Wide view, gives direction, knows what to ask: budget, actuals, forecast, cash flow. “A good understanding of everything… but not necessarily an expert” (on purpose).

From the conversation, ~55:08–1:03:30 · including Orion’s orchestra-conductor question
Quick Reference

Quote Bank

The best on-the-record lines, gathered in one filterable place. “Highlight” marks the lines most worth scrubbing back for; quotes are lightly condensed and timestamps are approximate.

Vision 2030 & the Path to Riyadh 0:00–6:12

  • Highlight“I’m really a problem solver. I bring order to chaos. And I think project controls does a lot of that: it brings order to chaos.”Jovita Stander · ~4:45
  • “What does it take to grow 7.5 million trees across the capital city?”Orion Matthews · 0:11
  • “Part of Vision 2030, which is obviously close to my heart, is to increase the representation of Saudi women in the workforce.”Jovita Stander · ~2:00
  • “Really I’m a gypsy at heart… I think I’ve chosen the right career. Or it chose me, I don’t know.”Jovita Stander · ~5:05

Anatomy of a $10B Urban Forest 6:12–16:23

  • Highlight“The irrigation will be done using treated sewage effluent… about 1,300 kilometres of irrigation network throughout the city; a hundred percent of the irrigation will be this type of water.”Jovita Stander · ~10:45
  • “When it rains, people are so happy they actually go out of the offices and film the rain. I just find that beautiful.”Jovita Stander · ~13:20
  • “The moment you see something green, it’s nice on the senses… it probably lifts your mood. At least it lifts mine.”Jovita Stander · ~14:30
  • “People in the neighborhood are at a maximum of 300 metres away from a green space, to encourage that healthy lifestyle.”Jovita Stander · ~15:05

A Program, Not a Project 16:23–25:09

  • Highlight“They talk about the Green Riyadh project, but in actual fact the project is a program… The park is not just a park, it’s almost like a smart park. Some of the parks actually have a stadium.”Jovita Stander · ~18:30
  • “I was actually sitting in my house in Katy, Houston, Texas, when I got a call out of the blue… I did a little bit of research, and I ended up here.”Jovita Stander · ~17:05
  • “You can’t dig up the whole city for the network; it’ll just be one big chaos… We don’t talk about phases; we talk about priorities.”Jovita Stander · ~19:50
  • “Every project controls team should have the graphic design under them. I’m just going to say that.”Jovita Stander · ~22:30
  • “One picture is more valuable than a thousand words, I suppose.”Jovita Stander · ~24:05

Where the Schedule Meets the Map 25:09–32:10

  • Highlight“Each of those little assets had a code, and those codes would tie back into P6… so we could always relate back; it doesn’t matter which database you were using.”Jovita Stander · ~27:30
  • “They identified, if I remember correctly, 72 species that are native to the area, a lot of acacias, which are thorn trees; we get them a lot in South Africa… of course palm trees.”Jovita Stander · ~30:20
  • “By using other species, still native, the canopy cover can still be achieved… instead of 7.5 million trees, it could be seven, and the same KPI can still be met.”Jovita Stander · ~31:20

Leading in a Sea of Men 32:10–38:51

  • Highlight“Standing in the boardroom, it was a sea of men in front of me… This really was the first time in my life that there was no other female in the boardroom.”Jovita Stander · ~33:00
  • “I had an option to assert my authority… or I could do it in a more subtle way. If you do it in a more pleasant way, you gain more in the long run.”Jovita Stander · ~34:40
  • “I would always be the last one going home. I would never leave before them and the work was finished.”Jovita Stander · ~36:10
  • Highlight“The wife and the kids are at home… so you also need to take that human element into consideration: a lot of things might be happening that are not apparent.”Jovita Stander · ~37:20
  • “Recognizing good work and giving credit where it’s due… I think that buys you as a leader a lot of miles.”Jovita Stander · ~38:20

High-Stakes Rooms 38:51–44:51

  • Highlight“I don’t have the answer for you now, Your Excellency, but I will get it to you as soon as we finish the meeting… I think you lose more credibility by trying to fudge it.”Jovita Stander · ~41:20
  • “You can never be prepared enough. Prepare.”Jovita Stander · ~39:30
  • “I’m an introvert by nature… The nature of project controls is to deal in facts: if you say it’s 54%, it doesn’t mean it’s 52%; it’s 54%.”Jovita Stander · ~43:45
  • “It takes a lot of courage to not weave and bob when you don’t know the answer… being able to tell people what they don’t want to hear is a real skill.”Orion Matthews · ~42:50

The Basics Before the Dashboards 44:51–54:38

  • Highlight“You need to start with the basics. And the basics is cutoff dates, so that everybody reports to the same cutoff date.”Jovita Stander · ~45:45
  • “If something is nagging and you’ve got that gut feeling, even if you can’t put your finger on it, rather go back and check.”Jovita Stander · ~48:15
  • Highlight“Is there a golden thread through your weekly reports that feeds into your monthly report? If you deconstruct the month, will it talk to the third week, the second and the first?”Jovita Stander · ~49:00
  • “It comes back to the old thing, garbage in, garbage out… these wonderful tools will not help the decision makers make good decisions for the project.”Jovita Stander · ~50:50
  • “There are so many moving parts… Project controls is the hub in getting all this information together.”Jovita Stander · ~53:10

Careers, Women & Mentors 54:38–1:10:39

  • “My short answer is: go for it.”Jovita Stander · ~55:15
  • “I’m an eternal learner, and I think in project controls you need to be that: you must always be learning something.”Jovita Stander · ~58:50
  • Highlight“Women have a different way of leadership, of addressing problems… It’s not that how the men do it is right or wrong, or how we do it is right or wrong, it’s just different.”Jovita Stander · ~1:05:00
  • “You never need to apologize for being a woman in this field… but you cannot be easily offended.”Jovita Stander · ~1:06:20
  • “I’ve been very, very blessed in this career. If I had a choice, I would do it all over again.”Jovita Stander · ~1:07:15
  • Highlight“Go to somebody that is already experienced and ask them: will you be my mentor?… When I ask for help, nobody has ever said to me, ‘No, I’m not going to help you.’”Jovita Stander · ~1:08:40